In order to promote safety and efficiency when moving oversized loads through Elkhorn Rural Public Power District, please download, complete and return the Oversized Permit Notification Form, ten days prior to the move.
Other labor and material fees may apply. Please contact ERPPD at (800) 675-2185 with any questions.
To see which electric utilities are on your path of travel, you can see a map of service territories by clicking on the link below which will take you to the Nebraska Power Review Board interactive map of service boundaries.
Nebraska Power Review Board System Map
* According to LB 973 which became law on July 20, 2016, electric utilities must be notified in writing ten days prior to when an oversized load is to be transported through their service territory. The transporter will be required to provide this proof to law enforcement upon request and failure to do so can result in a $1,000 fine. The fine for the manipulation of utility infrastructure has also increased to $1,000 per incident.